Bessie Stormwater & Drainage

 

 

 

Timeline

  • Additional survey – 3/01 – 3/22/2021
  • 45% Design Plans – 2/22 – 4/30/2021
  • Public Involvement Workshops and TC meeting – 5/03 – 6/08/2021
  • Geotech, utility test holes, survey to pick up test holes – 6/09 – 6/23/2021
  • Final Design Drainage Plans and Water Main Plans – 6/09 – 8/09/2021
  • Permitting – 6/09 – 9/09/2021
  • Public Involvement and TC meeting – 8/10 – 9/14/2021
  • Bid Plans – 9/15 – 10/15/2021
  • 90% Workshop – 12/2/2021
  • Utilities test hole dig – first week of January 2022